Estimating drilling cost and duration using copulas dependencies models

M. Al Kindi, M. Al-Lawati, N. Al-Azri

Research output: Contribution to journalArticle

Abstract

Estimation of drilling budget and duration is a high-level challenge for oil and gas industry. This is due to the many uncertain activities in the drilling procedure such as material prices, overhead cost, inflation, oil prices, well type, and depth of drilling. Therefore, it is essential to consider all these uncertain variables and the nature of relationships between them. This eventually leads into the minimization of the level of uncertainty and yet makes a "good" estimation points for budget and duration given the well type. In this paper, the copula probability theory is used in order to model the dependencies between cost/duration and MRI (mechanical risk index). The MRI is a mathematical computation, which relates various drilling factors such as: water depth, measured depth, true vertical depth in addition to mud weight and horizontal displacement. In general, the value of MRI is utilized as an input for the drilling cost and duration estimations. Therefore, modeling the uncertain dependencies between MRI and both cost and duration using copulas is important. The cost and duration estimates for each well were extracted from the copula dependency model where research study simulate over 10,000 scenarios. These new estimates were later compared to the actual data in order to validate the performance of the procedure. Most of the wells show moderate - weak relationship of MRI dependence, which means that the variation in these wells can be related to MRI but to the extent that it is not the primary source.

Original languageEnglish
Pages (from-to)1-9
Number of pages9
JournalJournal of Engineering Research
Volume14
Issue number1
Publication statusPublished - 2017

Fingerprint

Drilling
Costs
Gas industry
Water
Oils

Keywords

  • Archimedean copula
  • Mechanical risk index (MRI)
  • Monte Carlo simulation

ASJC Scopus subject areas

  • Engineering(all)

Cite this

Estimating drilling cost and duration using copulas dependencies models. / Al Kindi, M.; Al-Lawati, M.; Al-Azri, N.

In: Journal of Engineering Research, Vol. 14, No. 1, 2017, p. 1-9.

Research output: Contribution to journalArticle

@article{ac1fc45c828848e0954810a58dafb99b,
title = "Estimating drilling cost and duration using copulas dependencies models",
abstract = "Estimation of drilling budget and duration is a high-level challenge for oil and gas industry. This is due to the many uncertain activities in the drilling procedure such as material prices, overhead cost, inflation, oil prices, well type, and depth of drilling. Therefore, it is essential to consider all these uncertain variables and the nature of relationships between them. This eventually leads into the minimization of the level of uncertainty and yet makes a {"}good{"} estimation points for budget and duration given the well type. In this paper, the copula probability theory is used in order to model the dependencies between cost/duration and MRI (mechanical risk index). The MRI is a mathematical computation, which relates various drilling factors such as: water depth, measured depth, true vertical depth in addition to mud weight and horizontal displacement. In general, the value of MRI is utilized as an input for the drilling cost and duration estimations. Therefore, modeling the uncertain dependencies between MRI and both cost and duration using copulas is important. The cost and duration estimates for each well were extracted from the copula dependency model where research study simulate over 10,000 scenarios. These new estimates were later compared to the actual data in order to validate the performance of the procedure. Most of the wells show moderate - weak relationship of MRI dependence, which means that the variation in these wells can be related to MRI but to the extent that it is not the primary source.",
keywords = "Archimedean copula, Mechanical risk index (MRI), Monte Carlo simulation",
author = "{Al Kindi}, M. and M. Al-Lawati and N. Al-Azri",
year = "2017",
language = "English",
volume = "14",
pages = "1--9",
journal = "Journal of Engineering Research",
issn = "1726-6009",
publisher = "Sultan Qaboos University",
number = "1",

}

TY - JOUR

T1 - Estimating drilling cost and duration using copulas dependencies models

AU - Al Kindi, M.

AU - Al-Lawati, M.

AU - Al-Azri, N.

PY - 2017

Y1 - 2017

N2 - Estimation of drilling budget and duration is a high-level challenge for oil and gas industry. This is due to the many uncertain activities in the drilling procedure such as material prices, overhead cost, inflation, oil prices, well type, and depth of drilling. Therefore, it is essential to consider all these uncertain variables and the nature of relationships between them. This eventually leads into the minimization of the level of uncertainty and yet makes a "good" estimation points for budget and duration given the well type. In this paper, the copula probability theory is used in order to model the dependencies between cost/duration and MRI (mechanical risk index). The MRI is a mathematical computation, which relates various drilling factors such as: water depth, measured depth, true vertical depth in addition to mud weight and horizontal displacement. In general, the value of MRI is utilized as an input for the drilling cost and duration estimations. Therefore, modeling the uncertain dependencies between MRI and both cost and duration using copulas is important. The cost and duration estimates for each well were extracted from the copula dependency model where research study simulate over 10,000 scenarios. These new estimates were later compared to the actual data in order to validate the performance of the procedure. Most of the wells show moderate - weak relationship of MRI dependence, which means that the variation in these wells can be related to MRI but to the extent that it is not the primary source.

AB - Estimation of drilling budget and duration is a high-level challenge for oil and gas industry. This is due to the many uncertain activities in the drilling procedure such as material prices, overhead cost, inflation, oil prices, well type, and depth of drilling. Therefore, it is essential to consider all these uncertain variables and the nature of relationships between them. This eventually leads into the minimization of the level of uncertainty and yet makes a "good" estimation points for budget and duration given the well type. In this paper, the copula probability theory is used in order to model the dependencies between cost/duration and MRI (mechanical risk index). The MRI is a mathematical computation, which relates various drilling factors such as: water depth, measured depth, true vertical depth in addition to mud weight and horizontal displacement. In general, the value of MRI is utilized as an input for the drilling cost and duration estimations. Therefore, modeling the uncertain dependencies between MRI and both cost and duration using copulas is important. The cost and duration estimates for each well were extracted from the copula dependency model where research study simulate over 10,000 scenarios. These new estimates were later compared to the actual data in order to validate the performance of the procedure. Most of the wells show moderate - weak relationship of MRI dependence, which means that the variation in these wells can be related to MRI but to the extent that it is not the primary source.

KW - Archimedean copula

KW - Mechanical risk index (MRI)

KW - Monte Carlo simulation

UR - http://www.scopus.com/inward/record.url?scp=85020287540&partnerID=8YFLogxK

UR - http://www.scopus.com/inward/citedby.url?scp=85020287540&partnerID=8YFLogxK

M3 - Article

VL - 14

SP - 1

EP - 9

JO - Journal of Engineering Research

JF - Journal of Engineering Research

SN - 1726-6009

IS - 1

ER -