A decision support tool for bi-objective risk-based maintenance scheduling of an LNG gas sweetening unit

Abdul Hameed, Syed Asif Raza*, Qadeer Ahmed, Faisal Khan, Salim Ahmed

*Corresponding author for this work

Research output: Contribution to journalArticlepeer-review

18 Citations (Scopus)

Abstract

Purpose: The purpose of this paper is to develop a decision support tool for risk-based maintenance scheduling for a large heavily equipped gas sweetening unit in a Liquefied Natural Gas (LNG) plant. Two conflicting objectives, i.e., total maintenance cost and the reliability, are considered in the tool. The tool is tested with the real plant data and suggests several Pareto-optimal schedules for a decision maker to choose from. The financial impacts are assessed. Design/methodology/approach: A bi-objective scheduling optimization model is developed for maintenance scheduling using a risk-based framework. The model is developed integrating genetic algorithm and simulation-based optimization to find Pareto-optimal schedules. The model delivered true Pareto front optimal solutions for given plant-specific data. The two conflicting objectives: the minimization of total expenditures incurred on maintenance-related activities and improving the total reliability are considered. Findings: For large and complex processing facilities such as LNG plant, a shutdown of facility generates a significant financial impact, resulting in millions of dollars in production loss. The developed risk-based equipment selection strategy helps to minimize such an event of production loss by generating a thorough maintenance strategy for inspection, repair, overhaul or replacement schedule of the unit without initiating the shutdown. The proposed model has been successfully applied to obtain an optimize maintenance schedule for a gas sweetening unit. Research limitations/implications: A future work may consider the state-dependent models for various failure modes that will result in obtaining a better representation of the model. The proposed scheduling can further be extended to multi-criteria scheduling including availability, resource limitation and inflationary condition. A comparative analysis with other meta-heuristic techniques such as harmony search algorithm, tabu search, and simulated annealing will further help in confirming the schedule obtained from this application. Practical implications: Maintenance scheduling using a conventional approach for special equipment generally does not consider the conflicting objectives. This research addresses this aspect using a bi-objective model. The usefulness of risk-based method is to assist in minimizing the financial and safety risk exposure to the operating companies, but some variation in results is expected due to varying risk matrix for different organizations. Social implications: Managing two objectives, i.e., minimizing the cost of maintenance-related activities, while at the same time maximizing the overall reliability dramatically, helps in mitigating adverse safety and financial risk due to fires, explosions, fatality and excessive maintenance cost. Originality/value: Research develops a decision support tool for managing conflicting objectives for an LNG process. This research highlights the impact of utilizing the simulation-based approach coupled with risk-based equipment selection for complex processing unit or plant maintenance scheduling optimization.

Original languageEnglish
Pages (from-to)65-89
Number of pages25
JournalJournal of Quality in Maintenance Engineering
Volume25
Issue number1
DOIs
Publication statusPublished - Mar 4 2019

Keywords

  • Genetic algorithm
  • Liquefied natural gas (LNG) plant
  • Reliability
  • Risk-based maintenance
  • Shutdown
  • Simulation-based optimization

ASJC Scopus subject areas

  • Safety, Risk, Reliability and Quality
  • Strategy and Management
  • Industrial and Manufacturing Engineering

Cite this