TY - JOUR
T1 - A novel multi criteria decision making model for optimizing time-cost-quality trade-off problems in construction projects
AU - Monghasemi, Shahryar
AU - Nikoo, Mohammad Reza
AU - Khaksar Fasaee, Mohammad Ali
AU - Adamowski, Jan
N1 - Publisher Copyright:
© 2014 Elsevier Ltd. All rights reserved.
PY - 2015/4/15
Y1 - 2015/4/15
N2 - The planning phase of every construction project is entangled with multiple and occasionally conflicting criteria which need to be optimized simultaneously. Multi-criterion decision-making (MCDM) approaches can aid decision-makers in selecting the most appropriate solution among numerous potential Pareto optimal solutions. An evidential reasoning (ER) approach was applied for the first time in the context of project scheduling to identify the best Pareto solution for discrete time-cost-quality trade-off problems (DTCQTPs). An exhaustive framework to synthesize the MCDM approaches with multi-objective optimization techniques was also proposed. To identify all global Pareto optimal solutions, a multi-objective genetic algorithm (MOGA) incorporating the NSGA-II procedure was developed and tested in a highway construction project case study. The Shannon's entropy technique served to determine the relative weights of the objectives according to their contributions to the uncertainty of the results obtained. A benchmark case study of DTCQTP was solved using the proposed methodology, and the Pareto optimal solutions obtained were subsequently ranked using the ER approach. By investigating the performance of each scheduling alternative based on multiple criteria (e.g., time, cost, and quality), the proposed approach proved effective in raising the efficiently of construction project scheduling.
AB - The planning phase of every construction project is entangled with multiple and occasionally conflicting criteria which need to be optimized simultaneously. Multi-criterion decision-making (MCDM) approaches can aid decision-makers in selecting the most appropriate solution among numerous potential Pareto optimal solutions. An evidential reasoning (ER) approach was applied for the first time in the context of project scheduling to identify the best Pareto solution for discrete time-cost-quality trade-off problems (DTCQTPs). An exhaustive framework to synthesize the MCDM approaches with multi-objective optimization techniques was also proposed. To identify all global Pareto optimal solutions, a multi-objective genetic algorithm (MOGA) incorporating the NSGA-II procedure was developed and tested in a highway construction project case study. The Shannon's entropy technique served to determine the relative weights of the objectives according to their contributions to the uncertainty of the results obtained. A benchmark case study of DTCQTP was solved using the proposed methodology, and the Pareto optimal solutions obtained were subsequently ranked using the ER approach. By investigating the performance of each scheduling alternative based on multiple criteria (e.g., time, cost, and quality), the proposed approach proved effective in raising the efficiently of construction project scheduling.
KW - Construction projects
KW - Discrete time-cost-quality trade-off
KW - Evidential reasoning
KW - Multi-criterion decision-making
KW - Multi-objective optimization
KW - NSGA-II
KW - Shannon's entropy
UR - http://www.scopus.com/inward/record.url?scp=84919807757&partnerID=8YFLogxK
UR - http://www.scopus.com/inward/citedby.url?scp=84919807757&partnerID=8YFLogxK
U2 - 10.1016/j.eswa.2014.11.032
DO - 10.1016/j.eswa.2014.11.032
M3 - Article
AN - SCOPUS:84919807757
SN - 0957-4174
VL - 42
SP - 3089
EP - 3104
JO - Expert Systems with Applications
JF - Expert Systems with Applications
IS - 6
ER -